Analisis Potensi Pembangkit Listrik Tenaga Surya (PLTS) di Gedung Kantor Bupati Kabupaten Temanggung

Authors

  • Arum Damasari Program Studi Teknik Lingkungan, Fakultas Teknik, Universitas Proklamasi 45
  • Fitri Nur Afifah Program Studi Teknik Lingkungan, Fakultas Teknik, Universitas Proklamasi 45
  • Andri Prasetyo Nugroho Program Studi Teknik Lingkungan, Fakultas Teknik, Universitas Proklamasi 45 https://orcid.org/0000-0003-3896-5740

Keywords:

PVSyst, PLTS, Kabupaten Temanggung

Abstract

The government has targeted a 23% increase in the use of renewable energy by 2025. The Ministry of Energy and Mineral Resources (ESDM) in Indonesia has taken steps to achieve this goal by issuing Circular Letter No. 363/22/MEM.L/2019, urging the installation of rooftop solar power systems (PLTS) on buildings. In response to this directive, the office of the regent of Temanggung Regency has been designated for the installation of rooftop PLTS. To ensure the proper implementation of the PLTS installation, calculations were made to assess the potential, including observing the geographical location of the building, its condition, rainfall and climate intensity, as well as solar radiation intensity. The installation of the grid-connected PLTS took place at the main building of the regent's office in Temanggung. Simulations were conducted using PVSyst 7.2.6 software, resulting in an annual electricity potential of 3795 kWh. The solar panel modules used were mono 250 Wp 60 cell Bifacial models, totaling 11 units with a 30° elevation angle. The highest electricity potential occurs in July, with an array output of 449 kWh.

References

Al Hakim, R. R. (2020). Model Energi Indonesia, Tinjauan Potensi Energi Terbarukan untuk Ketahanan Energi di Indonesia: Sebuah Ulasan. Jurnal Pengabdian Kepada Masyarakat (ANDASIH), 1(1). https://doi.org/10.57084/andasih.v1i1.374

Builder Indonesia. (2021). PLTS Atap, Wajib Paham Ini Sebelum Memasang PLTSAtap.https://www.builder.id/plts-atap/

Databoks.katadata.co.id. (2021). Konsumsi ListrikPer Kapita Indonesia Capai 1.109kWH pada Kuartal III 2021.https://databoks.katadata.co.id/datapublish/2021/12/10/konsumsi-listrikper-kapita-indonesia-capai-1109kwh-pada-kuartal-iii-2021

Kompas.com.(2022). Jumlah Penduduk Indonesia2022. https://nasional.kompas.com/read/2022/04/27/03000051/jumlahpenduduk-indonesia-2022

Nugroho, A. P., & Kurniawan, D. (2021). Potensi Pembangkit Listrik Tenaga Surya Rooftop di Gedung Mohammad Hatta, Universitas Proklamasi 45. Jurnal Offshore: Oil, Production Facilities and Renewable Energy, 5(1), 12-19.http://dx.doi.org/10.30588/jo.v5i1.935

Ridho, M. A., Winardi, B., & Nugroho, A.(2019). Analisis Potensi Dan UnjukKerja Perencanaan PembangkitListrik Tenaga Surya (PLTS) DiDepartemen Teknik ElektroUniversitas DiponegoroMenggunakan Software Pvsyst 6.43.Transient: Jurnal Ilmiah TeknikElektro, 7(4), 883-890. https://doi.org/10.14710/transient.v7i4.883-890

Shofiyana, N., Supriyadi, I., Al Qarni, M. U. (2022). Transisi Energi Indonesia Pasca Pandemi Covid-19 dan Konflik Militer Rusia-Ukraina. Jurnal Kewarganegaraan, 6(2). https://doi.org/10.31316/jk.v6i2.3375

Downloads

Published

2024-08-13

How to Cite

Arum Damasari, Fitri Nur Afifah, & Andri Prasetyo Nugroho. (2024). Analisis Potensi Pembangkit Listrik Tenaga Surya (PLTS) di Gedung Kantor Bupati Kabupaten Temanggung. Jurnal Teknik Industri Manajemen Dan Manufaktur, 1(1), 16–24. Retrieved from https://ejournal.up45.ac.id/index.php/jtim/article/view/1863